Progress as of October 22, 2002
Get the Adobe Acrobat reader 
|
The site is taking shape.

Carpenters continue with framing at Homesite 23.

Carpenter installs wind up-lift tie at garage foundation.

Foundations complete at Homesites 28 and 29.

Plumbers install below grade waste lines at Homesite
4.

Excavation work begins at Homesite 1.